This case represents the Polish 400, 220 and 110 kV networks during winter 1999-2000 peak conditions. It is part of the 7500+ bus Europen UCTE system. To decrease the number of buses, the tie lines to foreign networks were replaced by artificial load or generator buses (180-186). Multiple generators at a bus have been aggregated. Generators that are not centrally dispatchable in the Polish energy market are given a cost of zero.
This data was graciously provided by, and is distributed with the permission of, Roman Korab (e-mail).